345kV Gangfeng-Zhongke, Zhongke-Hengshan Underground Transmission Line (Third Section)
The underground transmission line is located underneath the four shafts (above).
Continuing our strong track record in Taiwan, we have secured our eighth project: the 345kV Gangfeng-Zhongke, Zhongke-Hengshan Underground Transmission Line (Third Section) in Taichung, with a contract value of RM557.2 million (NTD 3.83 billion).
Awarded by Taiwan Power Company, this marks our second power infrastructure win, following the successful clinching of the award-winning 161kV Songshu to Guangfeng Underground Transmission Line in 2020.
The design and build contract span a 44-month timeline with the following scope of works:
- Civil engineering and auxiliary electrical and mechanical system works
- Construction of 4 shafts
- 3,208 m cable tunnel consists of different methods including tunnel boring machine, pipe jacking, open cut as well as acillary mechanical and eletrical works